The honest answer: most bathrooms take 2–5 days of tiling once the room is ready — but it depends on the size, the tile you’ve chosen and how much preparation the walls and floor need. Here’s a realistic breakdown so you can plan around it.

Rough timescales

By type of job

Shower or bath area only (walls)
1–2 days
Small bathroom (walls & floor)
2–3 days
Larger family bathroom
3–5 days
Wet room (with tanking)
add 1–2 days for tanking & leak test
Kitchen or hallway floor
1–3 days, depending on size & prep

These are tiling days, once the room is ready. Plumbing, plastering and fitting are separate.

What adds time

The things that stretch a job

  • Stripping out old tiles and making the walls or floor good again
  • Levelling an uneven floor or boarding out walls before tiling
  • Tanking a shower or wet room — it has to cure before tiling starts
  • Large-format, natural stone, herringbone and patterned layouts — slower to set out and cut
  • Underfloor heating, which needs the right adhesive and commissioning
  • Grout and silicone curing — around 24 hours before the room’s back in use

A typical small bathroom

Day by day

Day 1

Prep

Floors protected, old tiles stripped out if needed, the substrate levelled and boarded, and wet areas tanked and left to cure.

Day 2

Walls

Tiles set out from the focal point and fixed to the walls — cut neatly around niches, windows and fittings.

Day 3

Floor & finish

The floor laid, then everything grouted, siliconed, cleaned down and walked through with you.

Can it be done faster? Honestly, not without cutting the prep or the curing time — which is exactly where tiling jobs fail. Better to plan the days and get a finish that lasts. Wayne will give you a realistic timescale with your free quote, and stick to it.

Common questions

How long does it take to tile a small bathroom?

Around 2–3 days of tiling once the room is ready — roughly a day for prep and tanking, a day on the walls and a day for the floor, grouting and finishing.

Do I need to move out while my bathroom is tiled?

No. The house stays liveable — but that one bathroom is out of use while the work is on and for about 24 hours afterwards while the grout and silicone cure. If it’s your only bathroom, plan around it.

Why does a wet room take longer?

A wet room has to be fully tanked (waterproofed) and leak-tested before any tile goes down, and the tanking needs time to cure. That typically adds a day or two to a standard bathroom.

How soon can I use the shower after tiling?

Give the grout and silicone about 24 hours to cure before heavy use or a hot shower. Rushing it is how you end up with failed joints.

Related: what tiling costs · tiling services

Enquiries

Tell us about the room

Send over a few photographs and rough dimensions. We’ll come and see it, set out what’s involved and put a written price in your hands.